Sanitary Drainage and Vents
Drain, stack and vent sizes from drainage fixture units per IPC / UPC
International Plumbing Code 2021
Leave empty when the whole load enters at one floor.
Pumps, ejectors, equipment. 2 dfu per GPM.
Fixture units per IPC 2021 Table 709.1, continuous flow at 2 dfu per gpm (709.3). The building drain or sewer is the smallest size in Table 710.1(1) whose capacity at the slope reaches the total, 3″ or larger with a water closet (note a). The horizontal branch and stack come from Table 710.1(2): the stack column for three or fewer branch intervals or more than three, and the stack must also carry the most that enters one interval. Pipes with a water closet are 3″ or larger, since a closet’s 3″ outlet can’t drain into smaller pipe (704.2). The vent comes from Table 906.1 for the stack’s size, the load and the developed length to open air, never under half the stack or 1¼″ (906.1). This sizes one stack carrying the whole load; size each stack and branch with the load it carries. Offsets in buildings of five stories or more follow Section 711.
IPC 709.2: a fixture not listed takes the value for its outlet size in Table 709.2 (1¼″ 1 dfu, 1½″ 2, 2″ 3, 2½″ 4, 3″ 5, 4″ 6).
Enter or ↓ moves down · + and − step the count · paste a column from a spreadsheet to fill down
Values from IPC 2021 Table 709.1. A bathroom group counts as one; fixtures added to it add their own value (note f).